M
Mark
Hi
I have a task with 3 assigned resources and I use this task with a fixed work type (I don'
want the total work to change). At the beginning I have my 3 resources full (100%) and th
task duration is 3 months for a total work of 1836 hrs. I turn one assigned resource to 50
and the result duration is 6 months!!! Actually I'd want the work of my other assigned resource
to be updated too in order to get a shorter duration for my task (between 3 and 4 months a
my other 2 assigned ressources go on working...). I don't know how to get it.
I have a task with 3 assigned resources and I use this task with a fixed work type (I don'
want the total work to change). At the beginning I have my 3 resources full (100%) and th
task duration is 3 months for a total work of 1836 hrs. I turn one assigned resource to 50
and the result duration is 6 months!!! Actually I'd want the work of my other assigned resource
to be updated too in order to get a shorter duration for my task (between 3 and 4 months a
my other 2 assigned ressources go on working...). I don't know how to get it.