H
HJ
Hi Folks!
I have the following scenario in my project (MS
Project 2003):
ID Description
... ... (previous tasks)
14 Analisys
15 Meeting
16 Development
... ... (following tasks)
I want to (programmatically) create a task -
"Discussion" - between the 15th and 16th (see the example
below)
ID Description
... ... (previous tasks)
14 Analisys
15 Meeting
16 Discussion
17 Development
... ... (following tasks)
Obs: There is a method
named "Task.OutlineChildren.Add" that acctually creates a
task, however it is created in the last position of the
document.
Thanks!
HJ
I have the following scenario in my project (MS
Project 2003):
ID Description
... ... (previous tasks)
14 Analisys
15 Meeting
16 Development
... ... (following tasks)
I want to (programmatically) create a task -
"Discussion" - between the 15th and 16th (see the example
below)
ID Description
... ... (previous tasks)
14 Analisys
15 Meeting
16 Discussion
17 Development
... ... (following tasks)
Obs: There is a method
named "Task.OutlineChildren.Add" that acctually creates a
task, however it is created in the last position of the
document.
Thanks!
HJ