I am getting an overload on MS Project Workload Reports (******)

K

Ken

On the MS Project Report under Workload, Task Usage report, some of the hours
fields show all asterisks ********. Is this an overflow and how do I correct
it
 
J

JulieS

Hello Ken,

Select the Task Usage report and click the Edit button. Click the
Details tab and change the Date format to a longer format (Sun
1/27/02 for example). By increasing the date format, the columns
will be made wider and that should correct the asterisks. You may
also decrease the font size by using the "text" button, however most
people over 40 will not be pleased.


I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 