I can not see the tasks for each resource (including mine) on Pro.

H

Hemant D.

I have published my project on Project Server 2003. I can see the Project on
server but I cannot see the tasks associated to each resource (including
myself) on Server. I am getting message that there is no task assigned to
you.

I will apprecaite if someone will help me in fixing this issue.
 
R

Reid McTaggart

Did you use Build Team From Enterprise to assign resources to the project
before you assigned them to tasks? In the Build Team dialog box, are the
resource Booking types listed as Committed (not Proposed)?

Exactly what steps did you take to publish your project?

Reid McTaggart
(e-mail address removed)
Alegient, Inc.
Microsoft Certified Partner
Project Server Specialists
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top