I can't enter time on my timesheet

A

Andy Hohman

I can change the hours in the actual work column on the timesheet, but I
can't enter hours in for the individual days. Any ideas? Thanks.
 
D

Dale Howard [MVP]

Andy --

It sounds like your Project Server administrator has selected the Actual
Work Done and Work Remaining method of tracking progress in the system.
This restricts you to entering actuals in the task list on the left in the
Actual Work and Remaining Work columns only. If you need to enter actuals
in the timesheet grid on the right, refer your Project Server administrator
to the following FAQ's:

http://www.projectserverexperts.com/Shared Documents/trackingmethods.htm

http://www.projectserverexperts.com/Shared Documents/ChangeTrackingMethod.htm

Hope this helps.
 
B

btoms

I am having the same problem, and I have tried many different combinations on
the tracking progress screen with no luck. The links referenced in the
original response seem to be dead.

Thanks,
Bob
 
D

Dale Howard [MVP]

Bob --

The link is dead because we are moving are servers from our office in New
Jersey to a new office in the Financial District of NYC. Be patient and the
servers should be back up sometime today or tomorrow. If you are having a
problem similar to someone else's, then please post your question as a new
question so that everyone can learn from the problem and the solution. Hope
this helps.
 