hi
when I publish the plan in project server, tasks apear in "Projects" tab in
Microsoft Project Web Access but dont apear in every resource's "Tasks" Tab
in their Microsoft Project Web Access.
But when they "Create a new task" in their "Tasks" Tab it recieved in Plan
and I can accept it, and it apear in their "Tasks" Tab in their Microsoft
Project Web access.
We have a Project server2003,Users and every thing about our network is OK.
we inserted Users from "Active Directory".
The other problem that I think is concerned that problem is that I suppose
to see an yellow envelop with a red "!" Mark in "Indicators" column -its
ToolTip was about publish new or changed task information- that at peresent
time when I do any change on tasks information, it doesn't apear. and so many
tasks exsist that have the Icon but wen I publish plan in every way they dont
hid.
thanks
Iranian Realman
when I publish the plan in project server, tasks apear in "Projects" tab in
Microsoft Project Web Access but dont apear in every resource's "Tasks" Tab
in their Microsoft Project Web Access.
But when they "Create a new task" in their "Tasks" Tab it recieved in Plan
and I can accept it, and it apear in their "Tasks" Tab in their Microsoft
Project Web access.
We have a Project server2003,Users and every thing about our network is OK.
we inserted Users from "Active Directory".
The other problem that I think is concerned that problem is that I suppose
to see an yellow envelop with a red "!" Mark in "Indicators" column -its
ToolTip was about publish new or changed task information- that at peresent
time when I do any change on tasks information, it doesn't apear. and so many
tasks exsist that have the Icon but wen I publish plan in every way they dont
hid.
thanks