I Can't send resources' tasks to their "Tasks" tab/list in web acc

I

Iranian Realman

hi

when I publish the plan, tasks apear in "Projects" tab in Microsoft Web
Access but dont apear in every resource's "Tasks" Tab in their Microsoft Web
Access.
But when they "Create a new task" in their "Tasks" Tab it recieved in mail
Plan and I can accept it, and it apear in their "Tasks" Tab in Project Web
access.
Users and evbery thing about our network is OK.

The other problem that I think is about it is that when I suppose to see an
yellow envelop in "Indicators" column that at peresent time when do any
change on tasks information, it doesn't apear.

thanks

Iranian Realman
 
M

Mike Glen

Hi Iranian Realman,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
I

Iranian Realman

hi
thanks a lot Mike

ok, i'll do that.


Mike Glen said:
Hi Iranian Realman,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 