Ruth --
You might consider following a project planning methdology such as the
following:
1. Schedule your project using a Start date (Project - Project
Information - Start date)
2. Do task planning, including creating the task list, reordering the
tasks, building the Work Breakdown Structure (WBS), setting task Durations
wherever approrpiate, setting task dependencies, setting task Constraints
and Deadlines, set task Calendars wherever needed, and adding task Notes
wherever appropriate to document the project
3. Do resource planning by entering your project team in the Resource Sheet
view, or by building the project team using the Build Team from Enterprise
wizard (Project Server 2002 or 2003 only)
4. Do assignment planning by assigning your project team members to each
task in the project so that their task work is realistically modeled
5. Add a final project milestone (Duration = 0 days) called something like
"Project Complete" and link the milestone to the last task in the project
6. Examine the planned finish date of the project versus the contractual
finish date
7. If the project will finish later than the contractual finish date, you
can either replan the project with additional resources or renegotiate the
contractual finish date (just kidding!)
These are some ideas for you. Hope this helps.
ruth said:
i have a project to plan for which ought to have started on the 29th of
april and should end on the 7th of june all things being equal, how do i
start??