M
MelissaKae
This is so frustrating and happens every time I copy and paste from Excel
into Project and everything has the same start and end dates. I then put in
my links and durations. I would like the start dates to change based on the
predecessor and the duration. For example, task 2 is a predecessor for task
3. Task 2 has a duration of 2 days, from May 3 to May 4. I would like Task 3
to start on the next day and last 2 days. I change the duration, but the
start time remains the same as Task 2. I don't want to have to manually
change all the start dates, but I don't see a way to make the start dates
change.
into Project and everything has the same start and end dates. I then put in
my links and durations. I would like the start dates to change based on the
predecessor and the duration. For example, task 2 is a predecessor for task
3. Task 2 has a duration of 2 days, from May 3 to May 4. I would like Task 3
to start on the next day and last 2 days. I change the duration, but the
start time remains the same as Task 2. I don't want to have to manually
change all the start dates, but I don't see a way to make the start dates
change.