C
CMOSCAT
Our company rents containers, and recently decided that Project would be a
useful tool for planning and tracking. We currently have three different
batches with three different customers. I want to allocate those resources
as discrete batches, i.e. if we rent a batch of 120 containers to a customer
for 120 days, I want the resource usage to be 120 containers per day, not 1
container per day. I tried to treat the batches as a 'Work', rather than
'Material' resource but it didn't help. Because the containers are
identical, it's possible to change the absolute numbers in each batch, so
next year if customer A wanted less containers, we could 'transfer' the
surplus to customer B. In the short term, I'd want to do this by using 80%
of 'Resource A' with customer A, and adding 20% of 'Resource B' to customer
B. I appreciate that it will eventually become so complicated that we'll
'recalibrate' the batch sizes.
Thanks,
Donald Guthrie
Commercial Manager
useful tool for planning and tracking. We currently have three different
batches with three different customers. I want to allocate those resources
as discrete batches, i.e. if we rent a batch of 120 containers to a customer
for 120 days, I want the resource usage to be 120 containers per day, not 1
container per day. I tried to treat the batches as a 'Work', rather than
'Material' resource but it didn't help. Because the containers are
identical, it's possible to change the absolute numbers in each batch, so
next year if customer A wanted less containers, we could 'transfer' the
surplus to customer B. In the short term, I'd want to do this by using 80%
of 'Resource A' with customer A, and adding 20% of 'Resource B' to customer
B. I appreciate that it will eventually become so complicated that we'll
'recalibrate' the batch sizes.
Thanks,
Donald Guthrie
Commercial Manager