i want to generate S-curve

J

JulieS

Hi dharmendra,

MS Project cannot natively generate S-curves. I assume you wish to
create the S-curves for earned value information. The earned value data
can be exported to Excel by using the Analyze Timescaled Data in Excel
button on the Analysis toolbar.

Display the Task Usage view and show the Analysis toolbar. Click the
Analyze Timescaled Data in Excel... button. When the wizard runs,
select the earned value information (ACWP, BCWP, BCWS, CPI, SPI etc.)
that you wish to export. The wizard will ask if you wish to graph the
data as well.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
B

Bob C.

You could also export (or copy/paste) data to Excel and do some simple
calculations. Not very elegant, but it's doable.

-Bob C.
 

Ask a Question