J
Jamie Fristrom
If I use Standard levelling, and I have tasks that look
like this:
Task X Priority 1
Task Y Priority 2 Predecessors 1
Task Z Prioirty 3
Then it does task X first, then task Y, then task Z,
instead of Task Z (the highest priority), Task X, Task Y.
If I use Priority, Standard, that situation works, but then
this situation doesn't work:
Task X Priority 1
Task Y Priority 3 Predecessors 1
Task Z Priority 2
This should do Task X, then Task Y, then Task Z, but it
goes: Z, X, Y.
If I set the priority for task X to 3, accepting that
Project doesn't understand that being a predecessor to a
high-priority task implies that you're just as high a
priority, then it works, but I'm trying to migrate a
project from Excel that has about two-thousand tasks in it,
and I would need some way to automate the process. Is
there some way to automate the process so that priorities
are 'correct'?
like this:
Task X Priority 1
Task Y Priority 2 Predecessors 1
Task Z Prioirty 3
Then it does task X first, then task Y, then task Z,
instead of Task Z (the highest priority), Task X, Task Y.
If I use Priority, Standard, that situation works, but then
this situation doesn't work:
Task X Priority 1
Task Y Priority 3 Predecessors 1
Task Z Priority 2
This should do Task X, then Task Y, then Task Z, but it
goes: Z, X, Y.
If I set the priority for task X to 3, accepting that
Project doesn't understand that being a predecessor to a
high-priority task implies that you're just as high a
priority, then it works, but I'm trying to migrate a
project from Excel that has about two-thousand tasks in it,
and I would need some way to automate the process. Is
there some way to automate the process so that priorities
are 'correct'?