B
briancarroll101
I have an excel file that i use to forecast when certain actions are due to
be completed based on the working days it takes to process each action. I
wish to only display dates during the working week that are not public
holidays or during christmas leave. For example if I plan on having an action
complete on Monday the 5th and the next action takes 7 working days to
process it should be scheduled for completion on Wednesday the 14th, it is
not necessary for the days of the week to be displayed however
be completed based on the working days it takes to process each action. I
wish to only display dates during the working week that are not public
holidays or during christmas leave. For example if I plan on having an action
complete on Monday the 5th and the next action takes 7 working days to
process it should be scheduled for completion on Wednesday the 14th, it is
not necessary for the days of the week to be displayed however