ID Only Levelling - IDs renumbered by priority descending order

M

Michelle Moulliet

Does anyone have a levelling recommendation for levelling multiple projects
in enterprise server? In the client, I have only one file & I use ID only
levelling and I have the IDs set up to renumber by priority in descending
order. This has worked extremely well for me in the client with one file.

In enterprise, I have multiple project files set up which I intend to merge
into one master file. Resetting the IDs to number by priority only resets
the IDs at the project level and not at the task level. When I level by ID
only, it levels all of the tasks with ID number one in all of the projects,
then all of the tasks with ID number 2 in all of the projects. What I want
it to do is level each task in each high priority project then move to the
next priority project without using priority, standard as it's too random for
me. Does anyone have any suggestions?

Thanks!
 