T
Thomas Rose
We have an IT group that supports 50 applications and they wish to capture
support time by application during course of the year. During the course of a
week, any application or combination of applications can have support
requests, so it is different week to week and not predictable. Essentially we
are looking to park the time with appropriate application after the work is
complete.
We are using Project Server 2007 and have investigated the following:
1. Created a Annual Support workplan with a task per application in Project
Pro with the IT group added as Enterprise resources but not assigned to each
task. Problem with this solution was you cannot add Tasks in My Tasks and
adding the tasks to a Timesheet will allow you add only add Summary Task from
the workplan and you cannot import back into My Tasks. Thus Project Mgr of
the workplan never knows you work on that task.
2. Created Activity Plan, but you are forced to enter in duration and assign
resources to each task. You do not know up front what durations or who will
be assigned application support work in advance.
3. We looked at Team Assignments, but it appears that 50 tasks will be open
every week for a team member to sort through and accept, then reocrd time
against. Again we are looking to record time after the fact when support is
already done
Curious if anyone has a better mousetrap for this problem?
support time by application during course of the year. During the course of a
week, any application or combination of applications can have support
requests, so it is different week to week and not predictable. Essentially we
are looking to park the time with appropriate application after the work is
complete.
We are using Project Server 2007 and have investigated the following:
1. Created a Annual Support workplan with a task per application in Project
Pro with the IT group added as Enterprise resources but not assigned to each
task. Problem with this solution was you cannot add Tasks in My Tasks and
adding the tasks to a Timesheet will allow you add only add Summary Task from
the workplan and you cannot import back into My Tasks. Thus Project Mgr of
the workplan never knows you work on that task.
2. Created Activity Plan, but you are forced to enter in duration and assign
resources to each task. You do not know up front what durations or who will
be assigned application support work in advance.
3. We looked at Team Assignments, but it appears that 50 tasks will be open
every week for a team member to sort through and accept, then reocrd time
against. Again we are looking to record time after the fact when support is
already done
Curious if anyone has a better mousetrap for this problem?