Is there any way to tell when actual work was last updated on a task (i.e., a
modified date of some sort?)
I have a manager who wants to see a report of all tasks that should have had
actual work reported in the past 3 weeks, but have not. It's easy for
tasks that have no actual start, but I also need to get it for tasks that
have alraedy had actuals reported, just not in the past few weeks.
modified date of some sort?)
I have a manager who wants to see a report of all tasks that should have had
actual work reported in the past 3 weeks, but have not. It's easy for
tasks that have no actual start, but I also need to get it for tasks that