Y
Yoav
Hi, All
I have difficulties to identify by code dependencies (predecessors and
successors) of tasks in a Master Project where the dependent tasks are from
other projects.
For example: Task A from Project 1 is a predecessor to task B from project 2.
When I'm seeking by code the predecessors of task B, I find task A^ which is
an external task in project 2. I do not know how to connect between task A^
(external task) in project 2 to task A in project 1.
Does anyone have an idea?
I have difficulties to identify by code dependencies (predecessors and
successors) of tasks in a Master Project where the dependent tasks are from
other projects.
For example: Task A from Project 1 is a predecessor to task B from project 2.
When I'm seeking by code the predecessors of task B, I find task A^ which is
an external task in project 2. I do not know how to connect between task A^
(external task) in project 2 to task A in project 1.
Does anyone have an idea?