I am the Administrator, and I have set more than one inactive Pool
resource to have "Workgroup" equal "None" in the Resource Pool. They do stay
that way in subsequent re-opens of the Resource Pool. I also clear e-mail,
and Windows account, and they stay cleared.
However, when I open any Enterprise project with said resources
assigned, their resource information form has ALL the cleared fields named
above filled with the old information, and "Workgroup" set to "Default". If I
change the resource information fields to match the Enterprise Pool, it makes
no difference if I save or publish the project - reopening that project and
opening a Resource information form has all fields re-filled, and "Workgroup"
= "Default".
This is really more of nuisance than a problem, IMHO, but some PM's are
less tolerant than I am, and want it fixed.
Dale Howard said:
JC --
When you delete an enterprise resource, Project Server converts that
resource to a local resource in each project to which the resource is
assigned, and changes the resource's Workgroup value to None. When you
publish those project and then the OLAP cube rebuilds, the local resource
hours appear in the Status dimension in the Local Resources leaf. Thus,
Project Server accounts for all hours in all projects.
As you describe your problem with setting resources to Inactive, is your
Project Server administrator changing their Workgroup value to None in the
Enterprise Resource Pool, or are you doing this in a project? It must be
done in the Enterprise Resource Pool to make the setting "stick." Let us
know.
Jackson T. Cole said:
So, what happens to "actuals" of a deleted resource in the OLAP cube? If
the resouce is deleted in the middle of a fiscal period as presented in
the
cube, you don't the past to necessarily "disappear"!
"BTOJohn" didn't mention it, but in my projects with inactive pool
resources, I have to EXPLICITLY change their "Workgroup" state to "None"
EVERY TIME I Publish/Save the project! I tried using Resource Pool
management
to set "Workgroup", but that is the only place it stays "None". When I
re-open a project, all the inactives have "Workgroup" set to "Default",
their
old Windows account and email set right back to what they were when the
resource was active.
Hope someone still has entry flagged for a response! :>)
JC
:
John -
If you delete an inactive resource (assuming you are using Project
Server 2003), you will not lose actuals. The inactive resource will be
changed to a local resource with the words "deleted on [date] ..." plus
any other information you want to put in the line. You can do this
from Clean Up Project Server Database or by using PSCleaner, a free
download from Microsoft.
As far as finding out all instances of all local resources on all your
projects, I would suggest that you get with your DBAs to write a SQL
query. Some local resource data is available in the OLAP cube as a
total, so it's in the database. I don't know what the value is for a
local resource though. You will have to experiment by putting a known
project with a local resource on the server.
Mark