B
Bella
Hi,
We are using Project Server 2003 with PWA 2003 and MS Pro 2003. When a
resource submits her actual hours in PWA for a task an e-mail is sent to the
owner of that plan, who will then accept the update in PWA. However, instead
of the owner of the plan receiving the e-mail, I did and the updates showed
up in my PWA view. How did this happen? Has anyone else experienced this
problem?
I did publish some new and changed assignments on this plan. Could that be
the reason? But I never made myself the manager of the plan.
Thanks in advance,
Bella
We are using Project Server 2003 with PWA 2003 and MS Pro 2003. When a
resource submits her actual hours in PWA for a task an e-mail is sent to the
owner of that plan, who will then accept the update in PWA. However, instead
of the owner of the plan receiving the e-mail, I did and the updates showed
up in my PWA view. How did this happen? Has anyone else experienced this
problem?
I did publish some new and changed assignments on this plan. Could that be
the reason? But I never made myself the manager of the plan.
Thanks in advance,
Bella