K
Ken Kast
I want to model a situation where as soon as a resource becomes available a
task with another resource starts. The second task is a fixed work task.
Using the obvious SF relationship with ASAP tasks allows the first task to
start, then there can be a long lag until the second starts. In the real
world, by that time the resource may in fact no longer be available. The
first resource is really a material resource, but M S in it's project wisdom
has deemed that material is always available, and hence there's no calendar
associated with it. I can't assign both resources to the second task,
because I really need all the work done by the second resource.
I thought about trying to do this heuristically, trying to iterate to a
solution using resource leveling with a macro in between iterations playing
games with schedules. This isn't really a viable approach, because 1)
there's no guarantee it'll converge and 2) the project is so large that it
would take too long to run the iterations.
So, does anyone have a trick on how I can model this? BTW, I'm using
Proj2003, but ideally the solution would work going back to 2000.
Thanks.
Ken
task with another resource starts. The second task is a fixed work task.
Using the obvious SF relationship with ASAP tasks allows the first task to
start, then there can be a long lag until the second starts. In the real
world, by that time the resource may in fact no longer be available. The
first resource is really a material resource, but M S in it's project wisdom
has deemed that material is always available, and hence there's no calendar
associated with it. I can't assign both resources to the second task,
because I really need all the work done by the second resource.
I thought about trying to do this heuristically, trying to iterate to a
solution using resource leveling with a macro in between iterations playing
games with schedules. This isn't really a viable approach, because 1)
there's no guarantee it'll converge and 2) the project is so large that it
would take too long to run the iterations.
So, does anyone have a trick on how I can model this? BTW, I'm using
Proj2003, but ideally the solution would work going back to 2000.
Thanks.
Ken