impact of milestones on resource levelling / scheduling

J

JoGo

What differences (other than the obvious display difference) are there
between the ordinary tasks and tasks flagged as milestones?

In particular, is there a difference in teh way project resource levelling
and schduling for them?
 
J

Jan De Messemaeker

Hi,

Simply put, no. They are handled as any other task.
But when they have a zero duration, hence no work, they won't be leveled of
course.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
S

Steve House

And adding to Jan's comment, since milestones have no duration and thus no
work, they shouldn't have resources assigned to them either, thus "leveling"
a milestone to resolve resource overallocations makes no sense. A
milestone's location in the schedule is solely and completely determined by
the scheduling of its predecessor tasks.
 