A
anovak
Tell me if I'm barking up the wrong tree here but I think when you
first establish task dependencies you assume that all the resources
you need will be available.
Then, when you begin assigning resources, you may need to re-do task
sequences to reflect the "reality" that some tasks that otherwise
could be performed in parallel will have to be performed sequentially
given the resources available.
Is this the best way or is there preferred approach such as using
constraints, etc.?
Thanks,
Andy Novak
UNT
first establish task dependencies you assume that all the resources
you need will be available.
Then, when you begin assigning resources, you may need to re-do task
sequences to reflect the "reality" that some tasks that otherwise
could be performed in parallel will have to be performed sequentially
given the resources available.
Is this the best way or is there preferred approach such as using
constraints, etc.?
Thanks,
Andy Novak
UNT