J
jennifer.pickard
I saw in a previous posting someone asking about how they could import
the actual time from peoples excel timesheets into Project. The
recommendation was that they use a VBA to do this. I'm afraid I have
very little knowledge of VB but could probably change an existing VBA.
Does anyone have such a beast that I could try to change. The
information I need to import is very simple i.e.
<Resource Name> <Task> <Date> <Actual Time>
Previous Posting:
"Import actuals data from timesheets"
http://groups.google.co.uk/group/microsoft.public.project2000/browse_...
Is anyone able to help?
Many thanks
Jennifer
Import timesheet actuals from Excel into Project
the actual time from peoples excel timesheets into Project. The
recommendation was that they use a VBA to do this. I'm afraid I have
very little knowledge of VB but could probably change an existing VBA.
Does anyone have such a beast that I could try to change. The
information I need to import is very simple i.e.
<Resource Name> <Task> <Date> <Actual Time>
Previous Posting:
"Import actuals data from timesheets"
http://groups.google.co.uk/group/microsoft.public.project2000/browse_...
Is anyone able to help?
Many thanks
Jennifer
Import timesheet actuals from Excel into Project