I've exported the assignments from an existing schedule to Excel, this gives
me the proper structure; I've updated the hours leaving everything else
unchanged, and tried unsuccessfully to import the data back into MS Project
using WBS as the Merge Key. It doesn't work. What am I doing wrong? Thank
you.
The Excel export/import looks like this:
WBS Resource Work
1.2.1 Lead Engrg 10
1.2.2 Sr Engrg 20
1.2.3 Engrg B 30