When I import a project from primavera 6 into ms project 2003. ALL tasks are
given constrains even if ONLY FEW had them.
When this happens I cant seem to be able make any changes in scheduling due
to every single task having a constraint.
How can I get MSProject import without these added contrains (original
condition)?
alper
(e-mail address removed)
given constrains even if ONLY FEW had them.
When this happens I cant seem to be able make any changes in scheduling due
to every single task having a constraint.
How can I get MSProject import without these added contrains (original
condition)?