import/ constrains...?

A

alper

When I import a project from primavera 6 into ms project 2003. ALL tasks are
given constrains even if ONLY FEW had them.

When this happens I cant seem to be able make any changes in scheduling due
to every single task having a constraint.

How can I get MSProject import without these added contrains (original
condition)?

alper
(e-mail address removed)
 
J

Jan De Messemaeker

Hi,

If the importd tasks have start dates diffeent from teh project start date,
they will get constraints in Project I'm afraid
After the import, select the whoile Gantt Chart Sheet, click the Task
Information Button and in Advanced Tab click the constraint as soon as
possible.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top