L
Lorenzo
Need to update the Master schedule that resides at another Company. Our
Sub-Master schedule is updated in our company and is part of the Master
Schedule, but not linked because line #'s and wording do not match exactly.
We want to send progress updates to them, but only sections of our project
not the whole file, i.e. (column or task line). Our file is Project 2003.
Wht is the simplest way to do this? We are not connected to a shared Project
Server.
Thanks, Lorenzo
Sub-Master schedule is updated in our company and is part of the Master
Schedule, but not linked because line #'s and wording do not match exactly.
We want to send progress updates to them, but only sections of our project
not the whole file, i.e. (column or task line). Our file is Project 2003.
Wht is the simplest way to do this? We are not connected to a shared Project
Server.
Thanks, Lorenzo