Import Map trips up on dates defaulting

G

Guest

Whilst importing an excel project plan into Project, the
dates default to the project start date, how do I avoid
this ie to get the dates that are in the spreadsheet to
end up in the plan?
 
G

Gérard Ducouret

Hello,
If you import dates, you introduce date constraints.
Make sure the Project Start date is compatible with the dates your are
importing : Project / Project information...

Gérard Ducouret
 
D

David

I just ran into this problem myself. What I did was to open a blank project,
set the project start date, and then use the import wizard to append to the
project (versus creating a new one)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top