Used the import wizard to import three different projects
to the EPM Web. All resources were properly mapped.
Projects are published, appear in project centre, but
tasks do not appear for individuals assigned to them (no
tasks appear in users Task area).
Tried re-importing, same result.
Thought importing was supposed to give same results as
publishing?
to the EPM Web. All resources were properly mapped.
Projects are published, appear in project centre, but
tasks do not appear for individuals assigned to them (no
tasks appear in users Task area).
Tried re-importing, same result.
Thought importing was supposed to give same results as
publishing?