Import project to Enterprise 2007

N

Newbie

Hello,

I'm trying to import a mpp file in Project Server 2007.
One of the task has 2 resources : Ra assigned at 50% and Rb at 100%. Ra and
Rb are working 24 h each, but the Ra assignment is begining 3 weeks after
the task Start date.
When I import the project, the Ra workload jumps to 230 h.
Why ?
Thanks
 
B

Ben Howard

This could be an issue with the calendar. You'll need to be more specific re
the calendar types on the imported project, and make sure the same exist on
PS2007. Also, what is the current work for Ra before the import?
 
N

Newbie

Ben,

I think that an issue with the calendar could move somewhat the dates, but
not the workload of the assignment which jumped from 24h to 230 h !
Thanks
 
B

Ben Howard

Just a thought, how are you viewing the workload, via the resource sheet in
Project? If so, are you loading summary resource assignments when you load
Project, if so, you are now looking at all the work for that one resource.
What figure do you get if you insert the work colum in a gantt chart view?
 
G

Gérard Ducouret

I'm viewing the resource assignment workload in the Task Usage view.
The resource which was assigned only a few days (at 50%) at the end of the
task, is now (after the import) assigned every day (at 50%)
 