Hello,
I'm trying to import a mpp file in Project Server 2007.
One of the task has 2 resources : Ra assigned at 50% and Rb at 100%. Ra and
Rb are working 24 h each, but the Ra assignment is begining 3 weeks after
the task Start date.
When I import the project, the Ra workload jumps to 230 h.
Why ?
Thanks