G
Greg
Hi,
I did the following steps to import a project from one pws to another pws,
evething looks fine except timesheet.
1. Save the project as an .mpp file from source pws
2. Import this local project using Tools - Enterprise Options - Import
Project to
Enterprise to the new pws
3. Click Collaborate - Publish - All Information to publish the project
Eveything looks fine except timesheet.
1. I click View resource assignments under Resources, and select Timesheet
format, then I find out the "% Work Complete" is correct in left panel, but
the timesheet is blank for this project..
2. When resource logon to new pws and click Task -> View my tasks, "% work
Complete" is fine but all timesheet is blank for this project.
After find out this timesheet error in the new pws, I did one more testing
below:
1. Open MS Project and connect to the new pws, open this project in the new
pws, then select "Task Usage" view, it is surprise! I still can find out all
actual time in timesheet.
It looks like something wrong in pws, Any solution and suggestion is
welcome, thanks,
Environment: Project Server 2003 with SP1, and MS Project Professional 2003
in my local, and I have adminstrator right to both pws.
I did the following steps to import a project from one pws to another pws,
evething looks fine except timesheet.
1. Save the project as an .mpp file from source pws
2. Import this local project using Tools - Enterprise Options - Import
Project to
Enterprise to the new pws
3. Click Collaborate - Publish - All Information to publish the project
Eveything looks fine except timesheet.
1. I click View resource assignments under Resources, and select Timesheet
format, then I find out the "% Work Complete" is correct in left panel, but
the timesheet is blank for this project..
2. When resource logon to new pws and click Task -> View my tasks, "% work
Complete" is fine but all timesheet is blank for this project.
After find out this timesheet error in the new pws, I did one more testing
below:
1. Open MS Project and connect to the new pws, open this project in the new
pws, then select "Task Usage" view, it is surprise! I still can find out all
actual time in timesheet.
It looks like something wrong in pws, Any solution and suggestion is
welcome, thanks,
Environment: Project Server 2003 with SP1, and MS Project Professional 2003
in my local, and I have adminstrator right to both pws.