Hi,
We use MSP 2007 (SP1 but no infrastructure update)
When I am in a timesheet, the "Import Task Progress" unavailable
(grayed-out).
Does anyone have an idea what can cause that?
(The proccess I want to create: Team members update task progress
daily on My tasks page, and at the end of the week create their
timesheet and import the task progress into it . I prefer this method
than the other way around, becuase if they create the timesheet at the
begining of the week, in case they have a new assignment they will
need to use the annoying "add lines" feature).
Thanks for any help,
Gil.
We use MSP 2007 (SP1 but no infrastructure update)
When I am in a timesheet, the "Import Task Progress" unavailable
(grayed-out).
Does anyone have an idea what can cause that?
(The proccess I want to create: Team members update task progress
daily on My tasks page, and at the end of the week create their
timesheet and import the task progress into it . I prefer this method
than the other way around, becuase if they create the timesheet at the
begining of the week, in case they have a new assignment they will
need to use the annoying "add lines" feature).
Thanks for any help,