Import Time Into Excel

J

Johnnie

Not sure if I am posting on the right site.
Is there a way to import the scheduled work into Excel from MS Project
without the trailing h so I can sum the information?
I use PS 2003.
Thanks for all your help!

Johnnie
 
J

Jack Dahlgren

I think there is a setting somewhere which controls this, but even if you do
not have access, you can simply remove the h in excel using the "replace"
function. Simply replace all the h's with nothing.

-Jack Dahlgren
 