hello
i have a sheet for assignment in excel file . it has following field :
task id/ resource id/ task name/ resource name / work
the merge key is " resource id ". at the first time of importing data
everything is ok ; but when i change one of the data of work field , this
change isn't shown in MSP . WHY?