R
Rami
Hi
As you know when the resource changes the remaining availability and submit
the task for approval, it will reach the project manager as a new update.
How can the project manager know that this update will affect the schedule
since the duration now became longer? Imagine a project manager diving in a
big project plan and getting hundreds of updates each day. Is there any
indicator that can tell him if there is a change on the duration?
Thanks
As you know when the resource changes the remaining availability and submit
the task for approval, it will reach the project manager as a new update.
How can the project manager know that this update will affect the schedule
since the duration now became longer? Imagine a project manager diving in a
big project plan and getting hundreds of updates each day. Is there any
indicator that can tell him if there is a change on the duration?
Thanks