Reference: Project Server 2007 SP3

When importing projects to PWA, it happens the following events on a few
completed (100%) tasks after the project is imported, saved, published,
closed and reopened.

• Finish date disappears;
• % complete turn to 99%;
• Remaining work that was 0 is replaced by a value (variable).

I will appreciate any clue you might have.
 