A
Adrian Bates
I have used the Insert > Project function to insert a MS Project file into a
new template.
On doing the import I unchecked the "link to project" box to do a pure
import without maintaining a link to the original file.
The schedule imported fine with effort, durations and costs all being
identical in both schedules. Resource assignment data looks correct because
resource effort for each calendar month is identical in each schedule.
The problem is that the Work field (in the resource views) is set to 0h for
each resource. I cannot get this to recalculate.
Am I missing something obvious or is this a "feature" of MS Project.
Is there anything else I should be worried about having done this import?
The Project Manager needs confidence that the schedules are identical.
Many thanks,
new template.
On doing the import I unchecked the "link to project" box to do a pure
import without maintaining a link to the original file.
The schedule imported fine with effort, durations and costs all being
identical in both schedules. Resource assignment data looks correct because
resource effort for each calendar month is identical in each schedule.
The problem is that the Work field (in the resource views) is set to 0h for
each resource. I cannot get this to recalculate.
Am I missing something obvious or is this a "feature" of MS Project.
Is there anything else I should be worried about having done this import?
The Project Manager needs confidence that the schedules are identical.
Many thanks,