J
Jan
Thank you I appreciate the feedback.
The task is published and it's listed in PWA, since the resource was able to
select it and add it to their timesheet I assume that provided confirmation
however I'm also aware of the UID getting out of sync and have had the
project republished, deleted the added line and re-addded it. I also know we
can delete the timesheet, etc. as a work around.
What i want to know is why isn't the task listed for it to be imported from
the timesheets all the other tasks imported just fine. The task added is
listed in the timesheet for the resource who acatully entered time with a
category of Administration (is that the issue, if so how do i fix it). Where
it is not is in the import list in My Tasks, thus it doesn't get imported,
doesn't get submitted or approved and synced to the project schedule.
I can also see the task and time entered under Approvals/Timesheet under the
option of "available timesheets to adjust"
The task is published and it's listed in PWA, since the resource was able to
select it and add it to their timesheet I assume that provided confirmation
however I'm also aware of the UID getting out of sync and have had the
project republished, deleted the added line and re-addded it. I also know we
can delete the timesheet, etc. as a work around.
What i want to know is why isn't the task listed for it to be imported from
the timesheets all the other tasks imported just fine. The task added is
listed in the timesheet for the resource who acatully entered time with a
category of Administration (is that the issue, if so how do i fix it). Where
it is not is in the import list in My Tasks, thus it doesn't get imported,
doesn't get submitted or approved and synced to the project schedule.
I can also see the task and time entered under Approvals/Timesheet under the
option of "available timesheets to adjust"