Imported Timesheet missing tasks

J

Jan

Thank you I appreciate the feedback.

The task is published and it's listed in PWA, since the resource was able to
select it and add it to their timesheet I assume that provided confirmation
however I'm also aware of the UID getting out of sync and have had the
project republished, deleted the added line and re-addded it. I also know we
can delete the timesheet, etc. as a work around.

What i want to know is why isn't the task listed for it to be imported from
the timesheets all the other tasks imported just fine. The task added is
listed in the timesheet for the resource who acatully entered time with a
category of Administration (is that the issue, if so how do i fix it). Where
it is not is in the import list in My Tasks, thus it doesn't get imported,
doesn't get submitted or approved and synced to the project schedule.

I can also see the task and time entered under Approvals/Timesheet under the
option of "available timesheets to adjust"
 
J

Jan

So i figured it out, it is user error, i was under the assumption (bad jan i
know) that the Line classification was restricted to adding new timesheet
lines and not tasks, shame on me. Lesson Learned for sure and now I have to
go back and re-traing my users.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top