when I import an existing project into Project Server 2003, two things happen:
1. All the Task Duration, Start, and End dates get changed, which screws up
the project plan.
2. For tasks with multiple resoures, the Units % gets changed. For example,
Mike and Joe are assiged to the same task. Mike has a units % of 56% and Joe
has a units percent of 0%. After import, Mike has 236% and Joe has 0%
(expected).
I suspect its a problem with the project plan, but my client does have
enough experience with Project to troubleshoot it. Any ideas?
Thanks
1. All the Task Duration, Start, and End dates get changed, which screws up
the project plan.
2. For tasks with multiple resoures, the Units % gets changed. For example,
Mike and Joe are assiged to the same task. Mike has a units % of 56% and Joe
has a units percent of 0%. After import, Mike has 236% and Joe has 0%
(expected).
I suspect its a problem with the project plan, but my client does have
enough experience with Project to troubleshoot it. Any ideas?
Thanks