Importing a project plan into Project Server 2003

A

Anthony

when I import an existing project plan into Project Server 2003, two things
happen:

1. All the Task Duration, Start, and End dates get changed, which screws up
the project plan.

2. For tasks with multiple resoures, the Units % gets changed. For example,
Mike and Joe are assiged to the same task. Mike has a units % of 56% and Joe
has a units percent of 0%. After import, Mike has 236% and Joe has 0%
(expected).

I suspect its a problem with the project plan, but my client does have
enough experience with Project to troubleshoot it. Any ideas? We are running
SP1.

Thanks
 
M

Mike Glen

Hi Anthony,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top