when I import an existing project plan into Project Server 2003, two things
happen:
1. All the Task Duration, Start, and End dates get changed, which screws up
the project plan.
2. For tasks with multiple resoures, the Units % gets changed. For example,
Mike and Joe are assiged to the same task. Mike has a units % of 56% and Joe
has a units percent of 0%. After import, Mike has 236% and Joe has 0%
(expected).
I suspect its a problem with the project plan, but my client does have
enough experience with Project to troubleshoot it. Any ideas? We are running
SP1.
Thanks
happen:
1. All the Task Duration, Start, and End dates get changed, which screws up
the project plan.
2. For tasks with multiple resoures, the Units % gets changed. For example,
Mike and Joe are assiged to the same task. Mike has a units % of 56% and Joe
has a units percent of 0%. After import, Mike has 236% and Joe has 0%
(expected).
I suspect its a problem with the project plan, but my client does have
enough experience with Project to troubleshoot it. Any ideas? We are running
SP1.
Thanks