M
meg99
Using 2003 Pro. I need to import and XML file into MS Proj. I have a
userform and macro that does that but there is a problem.
I have a user form that provides the user with a choice of importing
an MPX file or an XML file. The MPX works well. As a part of the
import, I call up the "Change Working Time" dialog to allow the user
to select the appropriate calendar. When I import the XML file, many
of the "Change Working Time" objects/command buttons etc do not
display. When I go thru this process manually (File, Open, XML) etc,
and then select "Change Working Time", everything works fine.
Is there a way to "refresh" the "Change Working Time" dialog after it
displays?
Is there any reason the "Change Working Time" dialog would behave
differently when called from a macro?
meg99
userform and macro that does that but there is a problem.
I have a user form that provides the user with a choice of importing
an MPX file or an XML file. The MPX works well. As a part of the
import, I call up the "Change Working Time" dialog to allow the user
to select the appropriate calendar. When I import the XML file, many
of the "Change Working Time" objects/command buttons etc do not
display. When I go thru this process manually (File, Open, XML) etc,
and then select "Change Working Time", everything works fine.
Is there a way to "refresh" the "Change Working Time" dialog after it
displays?
Is there any reason the "Change Working Time" dialog would behave
differently when called from a macro?
meg99