amstar34
Our labor estimates for projects are initially developed in Excel. The
spreadsheet contains tasks, total work, resources, and assignment work. I
would like to be able to import tasks, resources, and assignment work into
Project 2003. Currently, I am able to import tasks, total work, and
resources, but I cannot find a field to import the assignment work into.
I have gone through the trouble to determine how to import multiple
resources into a single task, but each resource's respective portion of the
work (assignment work) is eluding me. For example, a 30 hour task (total
work) can be completed by employee 1 (resource) working 10 hours (assignment
work) and employee 2 (resource) working 20 hours (assignment work). We need
to be able to track this level of detail, so relying on only total work is
not a solution.
Each row in the spreadsheet represents one task, with multiple resources and
their respective assignment works. The total work is summed from the
collective assignment works.
How can I import multiple resources with their respective assignment work
directly into Project 2003 from Excel? Is there an import field for
assignment work in Project 2003?
Thank you,
spreadsheet contains tasks, total work, resources, and assignment work. I
would like to be able to import tasks, resources, and assignment work into
Project 2003. Currently, I am able to import tasks, total work, and
resources, but I cannot find a field to import the assignment work into.
I have gone through the trouble to determine how to import multiple
resources into a single task, but each resource's respective portion of the
work (assignment work) is eluding me. For example, a 30 hour task (total
work) can be completed by employee 1 (resource) working 10 hours (assignment
work) and employee 2 (resource) working 20 hours (assignment work). We need
to be able to track this level of detail, so relying on only total work is
not a solution.
Each row in the spreadsheet represents one task, with multiple resources and
their respective assignment works. The total work is summed from the
collective assignment works.
How can I import multiple resources with their respective assignment work
directly into Project 2003 from Excel? Is there an import field for
assignment work in Project 2003?