Dunlavy

I can not get the duration field to import into Project from either Excel or Access. What format do I need to be able to do so,

thank

Michael
 
D

Dunlavy

Never mind...figured out I was importing start and date finishes that didn't match duration time.....also, couldn't import hours, only days....
 