L
LarryG
in importing a project .mpx file, an export from Primevera, durations show up
as elapsed durations which is what is desired. The durations are imported as
hours, the macro to convert to days works fine.
When the schedules are inserted into a master schedule, the begin and end
date are consistent with the original elapsed durations.
When the schedules are copied into a new schedule, the end dates all run
long. It appears the 5 workdays per week applies to these tasks.
How can i change the duration from days to edays? Any macros out there to
fix this?
LarryG
as elapsed durations which is what is desired. The durations are imported as
hours, the macro to convert to days works fine.
When the schedules are inserted into a master schedule, the begin and end
date are consistent with the original elapsed durations.
When the schedules are copied into a new schedule, the end dates all run
long. It appears the 5 workdays per week applies to these tasks.
How can i change the duration from days to edays? Any macros out there to
fix this?
LarryG