I have a "master" project plan and receive updates from another project plan.
I've tried inserting and linking the project plan, but each line item from
the secondary plan needs to embedded into a different line item in the master
plan, rather than just at the bottom of the current project.
I've mapped the secondary plan into an excel file, and identify each line
item by a uniqueID. I then import this into the master plan, using the unique
ID as a merge key into text30 (which is pre-populated with the corresponding
number, to tell the import where to place the new data).
This updates the master plan with the imported data, but every other line
reverts back to the project start date - is there any way around this? Or is
there an easier way to import data into a project, from another project file,
but in a way that line items can be integrated....ie. so it doesn't just
stick it at the bottom of the existing project.
any help would be greatly appreciated.
I've tried inserting and linking the project plan, but each line item from
the secondary plan needs to embedded into a different line item in the master
plan, rather than just at the bottom of the current project.
I've mapped the secondary plan into an excel file, and identify each line
item by a uniqueID. I then import this into the master plan, using the unique
ID as a merge key into text30 (which is pre-populated with the corresponding
number, to tell the import where to place the new data).
This updates the master plan with the imported data, but every other line
reverts back to the project start date - is there any way around this? Or is
there an easier way to import data into a project, from another project file,
but in a way that line items can be integrated....ie. so it doesn't just
stick it at the bottom of the existing project.
any help would be greatly appreciated.