K
KLR
I am trying to Import a set of Resources with Estimated Hours(Work) per Resource per Task from an Excel spreadsheet and match these resources with their respective Tasks in Project 2003. I am not having much success. I have tried merging the resources to the task lists but only one resource is assigned to the task even if there are multiple resources per task. Does anyone know how to overcome this?
Basically i have a spreadsheet with the following;
Task No.1 Resource1 8hrs
Task No.1 Resource2 4hrs
Task No.1 Resource3 2hrs
Task No.2 Resource1 2hrs
Task No.2 Resource2 2hrs and so on...
I need to match the resources and work with the respective Task numbers.
Thanks in advance.
Basically i have a spreadsheet with the following;
Task No.1 Resource1 8hrs
Task No.1 Resource2 4hrs
Task No.1 Resource3 2hrs
Task No.2 Resource1 2hrs
Task No.2 Resource2 2hrs and so on...
I need to match the resources and work with the respective Task numbers.
Thanks in advance.