Importing Schedules to Project Server 2007

K

Karen M

I am trying to import existing schedules that were created with Project Pro
2007 into Project Server 2007 using the Enterprise Option, Import Project to
Enterprise, under Tools. I am mapping the local resources to the enterprises
resources; however, I'm getting the error "Resource Name Already in Use" on
most of my mapped resources. I can't figure out what I'm supposed to do.
This process also seems to be adding duplicated resources to some of the
tasks in the schedule.
 
J

Jonathan Sofer [MVP]

Have you upgraded to SP1 and Infrastructure Upgrade? I believe this was an
issue pre SP1. You could try to use the Save As option and "Replace All"
when prompted about existing resource names. This is another way to import
a schedule rather than Import Project.

Jonathan
 
J

Jonathan Sofer [MVP]

Check the queue for any failed jobs including user synchronization failed
jobs.

Jonathan
 
J

Jonathan Sofer [MVP]

Have you upgraded to SP1 and Infrastructure Upgrade? I believe this was an
issue pre SP1. You could try to use the Save As option and "Replace All"
when prompted about existing resource names. This is another way to import
a schedule rather than Import Project.

Jonathan
 