M
Marvin Brown
I'm exporting task information from our task management system into M
Project 2000.
After importing, I would like to create a summary task which indicate
the start/finish dates and total durations of all the tasks that I'v
just entered.
I've tried importing the tasks then inserting a new task and the
indenting all the imported tasks thus making the imported tasks subtask
of the new inserted task. Although the new inserted task is now
summary task, it does not display the overall stats of all th
subtasks.
What are my options?
Thank yo
Project 2000.
After importing, I would like to create a summary task which indicate
the start/finish dates and total durations of all the tasks that I'v
just entered.
I've tried importing the tasks then inserting a new task and the
indenting all the imported tasks thus making the imported tasks subtask
of the new inserted task. Although the new inserted task is now
summary task, it does not display the overall stats of all th
subtasks.
What are my options?
Thank yo