Importing tasksheets from Excel - Project 2007

M

Mike F

I see there is a way to export your tasksheet to Excel and it gives you a
very clean spreadsheet where we can track total actual hours/week more
effectively. The question that was posed is, "Can we update actuals in Excel
and import to our task sheet for submission?".

I don't see of a way, but thought I'd ask the experts!
 
D

Dale Howard [MVP]

Mike F --

Nope. The interaction between Excel and the My Tasks page or the My
Timesheet page is strictly one way: From PWA to Excel, but not the reverse.
Hope this helps.
 
M

Mike F

Thought that was the case.

Thanks Dale!!

Dale Howard said:
Mike F --

Nope. The interaction between Excel and the My Tasks page or the My
Timesheet page is strictly one way: From PWA to Excel, but not the reverse.
Hope this helps.
 