Improper value for Cost in Data Analysis reprts

J

Jaishree

Hi All,

I get improper value for Cost Fields in Data Reports.
For ex: if the actual cost is 5000 the Report says it as 4995.99
If budget cost is 80,000 report shows as 799997.867

Why does this happen how to rectify the same.
The project center Views and the Data reports all show the correct values.
This happens only with the data Analysis reports.
Please help.
 
P

Paul Conroy

Does the date range of the cube build/report cover the entire project
schedule ?
 