J
jen m
I am trying to split a task that has 12 hours so far split over several days.
I am trying to show that 4.5hrs were put on the task the first day, 6.5 the
second day and 2 hrs the 3rd day plus there are a few more hours of work
remaining. How do I split the task this way?
I am trying to show that 4.5hrs were put on the task the first day, 6.5 the
second day and 2 hrs the 3rd day plus there are a few more hours of work
remaining. How do I split the task this way?